PRCS conducted feasibility studies, design, and cost estimation for the development of basic infrastructure at Pelkarzhing Lap in Phuntsholing, Bhutan.
Name of the Client:
Phuntsholing Thromde
Project Description:
The main objective of this assignment was to prepare Detail Project Report (DPR) of all the basic Infrastructure for
Pelkarzhing LAP, Phuentsholing Thromde through the following stages:
A. To carry out a Feasibility study the tasks carried out were: –
- Conduct detailed field study for data and information collection
- Conduct detailed engineering survey and data collection.
- Analyze data, design, and provide alternate.
- Carry out analysis including economic, social, environmental, financial impact assessment analysis and other aspects.
- Organize presentation and consultation meeting if required.
- Conduct field verification and additional data collection if required.
- Submit final feasibility study report to Thromde with incorporation of all the comments and feedback.
B. To carry out detail Design and Estimate of the basic infrastructure :
- Carry out the Detailed Design & Drawing.
- Preparation of Detailed BoQ, Estimates, and Specifications.
- Preparation of Tender Documents.
Scope of work:
- Carry out the Detailed Design & Drawing.
- Preparation of Detailed BoQ, Estimates, Specifications and Tender Documents.
Specific details of the works are:
- Roads & Drains- Total Length- 17964 m (width-18.6m, 12m, 10m, 9m, 6m, & 4.5m)
- Total No of Culverts- 43.
- Water Supply Network-Total Length- 24640m, Water Reservoirs designed- 150, 300, 350, 500 Cum.
- Street Light- Total Length- 18610m.
- Footpath & Storm Water Drainage- Total Length Footpath- 645m & Total Length Drains- 6900m.
- Sewerage network- Total Network Length- 16300m & Treatment plant- 1MLD.